Create a Project Plan timeline #9

@hopeseekr

Description

@hopeseekr

Create a schedule for completion of various tasks.

  1. Just make it a simple time estimate based upon the Kanban board.
  2. Assume 3 hours per Effort point for worst case, 1 hour per Point for best case.
  3. Assume 4 hours worked per day.
  4. Account for dead (no work) days.